In short
You have 14 days from service to respond in writing. You can consent, or dissent and either agree to the building owner's surveyor acting as agreed surveyor or appoint your own surveyor. If you don't respond, a dispute is assumed. The building owner normally pays the reasonable fees of the surveyor you appoint.
Your options
| Option | What it means | Good for |
|---|---|---|
| Consent | Work can go ahead with no award or schedule of condition | Minor work and neighbours you trust |
| Dissent and agree an 'agreed surveyor' | One impartial surveyor prepares the award for both of you | Most domestic projects |
| Dissent and appoint your own surveyor | Your surveyor and theirs agree the award together | Larger or riskier work, basements, commercial schemes |
| Do nothing | After 14 days a dispute is assumed; after a further 10-day request the building owner can appoint a surveyor for you | Not recommended |
Why many neighbours dissent
Dissenting isn't hostile. It simply means a surveyor records the condition of your property before work starts and the work is controlled by an award. If something cracks, there's a clear record to work from.
Check the notice is valid
- Does it name all owners, including leaseholders?
- Is the correct section used, and is the notice period long enough?
- Does a Section 6 notice include plans and sections?
- Was it properly served?
We can act for you
As adjoining owner's surveyor we'll check the notice, review the drawings, prepare a schedule of condition of your property and agree an award that protects you. Our reasonable fees are normally paid by the building owner.
Common questions
Do I have to pay for my own surveyor?
Normally no. The building owner usually pays the reasonable fees of the adjoining owner's surveyor because the work is for their benefit.
Can I stop my neighbour's work?
The Act doesn't give you a veto over notifiable work. It gives you protection: an award controlling how the work is done, and the right to compensation for damage.
What if work has already started without notice?
Contact us quickly. We can write to the building owner and, if needed, you may be able to seek an injunction. See party wall disputes.
Source: Party Wall etc. Act 1996 (applies in England and Wales).