Step by step: how to serve a party wall notice

How to prepare, serve and follow up a party wall notice correctly.

By Guy Crouch MRICSReviewed 3 November 2026

In short

Identify the sections that apply, find every adjoining owner, prepare a notice with the required details and drawings, serve it properly with proof, and diary the 14-day response deadline.

The steps

  1. Confirm which sections apply (1, 2 and/or 6)
  2. Find all owners on HM Land Registry, including leaseholders
  3. Prepare the notice: names, addresses, work description, start date, and plans for Section 6
  4. Serve it by hand, post, or email if agreed
  5. Diary 14 days for a response
  6. Follow up if there's no reply

Common mistakes

  • Missing an owner, such as a leaseholder or joint owner
  • Using the wrong section, or too short a notice period
  • No drawings with a Section 6 notice
  • No proof of service

Do it yourself or use a surveyor

For a simple project you can use our £100 notice generator. For anything more complex, we'll draft and serve the notices for you.

Common questions

Can I email a party wall notice?

Only if the neighbour has agreed to receive notices by email. Otherwise serve by hand or post.

Source: Party Wall etc. Act 1996 (applies in England and Wales).

Written by Guy Crouch BSc (Hons) MRICS, Director and Chartered Building Surveyor at Manchester Party Wall Surveyors. Last reviewed 3 November 2026. This page is general guidance, not legal advice. About our team