Step by step: how to serve a party wall notice
How to prepare, serve and follow up a party wall notice correctly.
RICS member firm
- Free initial consultation
- 5.0 from 15 Google reviews
In short
Identify the sections that apply, find every adjoining owner, prepare a notice with the required details and drawings, serve it properly with proof, and diary the 14-day response deadline.
The steps
- Confirm which sections apply (1, 2 and/or 6)
- Find all owners on HM Land Registry, including leaseholders
- Prepare the notice: names, addresses, work description, start date, and plans for Section 6
- Serve it by hand, post, or email if agreed
- Diary 14 days for a response
- Follow up if there's no reply
Common mistakes
- Missing an owner, such as a leaseholder or joint owner
- Using the wrong section, or too short a notice period
- No drawings with a Section 6 notice
- No proof of service
Do it yourself or use a surveyor
For a simple project you can use our £100 notice generator. For anything more complex, we'll draft and serve the notices for you.
Common questions
Can I email a party wall notice?
Only if the neighbour has agreed to receive notices by email. Otherwise serve by hand or post.
Source: Party Wall etc. Act 1996 (applies in England and Wales).