In short
Most party wall questions come down to three things: whether your work needs notice (Sections 1, 2 and 6), what happens if your neighbour doesn't agree (surveyors and an award), and who pays (usually the building owner). Answers to the details are below.
| Notice | When it applies | Minimum notice | Neighbour's reply window |
|---|---|---|---|
| Section 1 line of junction | New wall on or astride the boundary | 1 month | 14 days |
| Section 2 party structure | Work to an existing party wall, floor or structure | 2 months | 14 days |
| Section 6 adjacent excavation | Digging within 3 m or 6 m of a neighbour's building, below its foundations | 1 month | 14 days |
Notices
Do I need a party wall surveyor, or can I serve the notice myself?
You can serve the notice yourself. The Act doesn't require a surveyor. But a notice with the wrong section, missing details or incorrect service can be invalid, so many owners use a surveyor to avoid delays.
How must a party wall notice be served?
In writing, describing the proposed work. It can be handed to the owner, posted to their usual or last known address, or sent electronically if they've agreed to receive notices that way.
What if the notice doesn't arrive?
If it can't be shown that it was served, it may be invalid. Keep proof of service, such as a signed acknowledgement or proof of posting.
What if I don't know who the adjoining owner is?
Check HM Land Registry. Where the owner can't be found after reasonable enquiries, the notice can be addressed to 'the owner' of the premises and fixed to a conspicuous part of the property.
Do leaseholders need to be served too?
Yes. 'Owner' under the Act includes freeholders and leaseholders with a term of more than a year, so a building with flats may need several notices.
What is the line of junction?
The legal boundary between two properties. Building on or astride it needs a Section 1 notice.
I don't know how deep my neighbour's foundations are. Do I need a Section 6 notice?
If you'll dig within 3 m of their building, it's safest to assume your foundations will be deeper and serve notice. A surveyor can advise, and trial holes can confirm.
Responses and surveyors
What if my neighbour doesn't respond?
After 14 days with no response, a dispute is assumed. You then write asking them to appoint a surveyor. If they don't within 10 days, you can appoint a surveyor to act for them under section 10(4).
If several neighbours dissent, can each appoint their own surveyor?
Yes. Each adjoining owner can appoint their own surveyor, which increases cost and time. Agreeing on one surveyor per boundary, or one agreed surveyor, is more efficient.
What is a third surveyor?
When each owner appoints their own surveyor, the two surveyors select a third surveyor at the start. If they can't agree on something, it's referred to the third surveyor, whose decision is binding, subject to appeal.
Are surveyors on my side?
Every surveyor appointed under the Act must act impartially and in line with the Act, whoever appointed them.
Costs
Who pays for party wall surveyors?
Usually the building owner, including the reasonable fees of the adjoining owner's surveyor. The surveyors can decide otherwise in the award, for example where the neighbour has asked for work for their own benefit.
Do surveyors charge fixed fees or hourly rates?
Either. We quote fixed fees where the scope is clear, and agree hourly rates in advance for complex or disputed matters.
Who pays the third surveyor?
The third surveyor decides who pays their fees, usually the building owner, unless one party has acted unreasonably.
What other costs might a building owner face?
Structural engineer's review, security for expenses on higher-risk work, and making good any damage caused.
Can the neighbour's surveyor's fees be challenged?
Yes, through the third surveyor, or by appeal to the county court within 14 days of the award.
Disputes and problems
What if I start work without serving notice?
The neighbour can seek an injunction to stop the work and may claim for any damage. You could also face legal costs. Serving notice from the start avoids this.
I didn't know about the Act and the work is finished. What now?
Speak openly with your neighbour. If there's no damage and no concern, it may go no further. If a dispute arises you may still be liable for damage; a surveyor's assessment and legal advice can help.
My house became an end-terrace after the neighbouring house was demolished. What does that mean?
The exposed party wall now needs weatherproofing. Under the Act, the owner who demolished must make good the exposed wall. Insulation or render may also need planning or building regulations approval.
Can the Act be misused?
It can, through excessive fees or delay. Clear notices, early conversations with neighbours and an experienced, impartial surveyor reduce the risk.
Commercial
Does the Party Wall Act apply to commercial buildings?
Yes. The Act applies to all buildings in England and Wales, including offices, shops, warehouses and mixed-use schemes.
Does the Act cover crane oversail or scaffolding on a neighbour's land?
No. Section 8 access rights only cover work needed for notifiable works. Crane oversail and most scaffold access need a separate licence agreed with the neighbour.
When should a developer appoint a party wall surveyor?
At design stage. Foundation design and boundary details determine which notices you need, and award timescales should be built into the programme.