Section 2: work to an existing party wall

The party structure notice: what work it covers, the two-month notice period, and your neighbour's options.

By Guy Crouch MRICSReviewed 3 November 2026
New-build semi-detached brick houses
Photo: James Feaver / Unsplash

In short

Serve a Section 2 party structure notice at least 2 months before work to an existing party wall, party fence wall or party floor. That includes cutting in steel beams, removing chimney breasts, raising or underpinning the wall, and cutting in flashings. Your neighbour has 14 days to consent; if they don't, a dispute is assumed and surveyors are appointed.

What counts as a party wall

The Act defines a party wall as either a wall standing on both owners' land that forms part of a building, or the part of a wall that separates buildings belonging to different owners. In Manchester that's the wall between terraced or semi-detached houses. Party structures also include floors and partitions between flats owned separately.

Work that needs a Section 2 notice

  • Cutting into a party wall to take the bearing of a steel beam, common in loft conversions and knock-throughs
  • Cutting away a projecting chimney breast, jamb or flue (chimney breast removal)
  • Raising a party wall, for example for a dormer or a higher roof
  • Underpinning or thickening a party wall, including in basement work
  • Demolishing and rebuilding a defective party wall
  • Cutting into the neighbour's wall to insert a flashing
  • Inserting a damp-proof course into a party wall

Minor works such as fixing shelves, kitchen units or sockets into a party wall don't usually need notice.

Timescales

StepTiming
Notice servedAt least 2 months before work starts
Neighbour respondsWithin 14 days, or a dispute is assumed
Neighbour's counter notice (optional)Within 1 month of your notice
Notice lapses if work hasn't started12 months after service

Counter notices

Your neighbour can reply with a counter notice asking for extra work for their own benefit, such as deeper foundations or chimney copings. They pay for anything done purely for them.

Access to the neighbour's property

Section 8 gives you, your builders and surveyors the right to enter the neighbour's property when needed for the notified work, on 14 days' notice (except in an emergency). The party wall award normally sets out how access works.

Common questions

How long does a Section 2 notice last?

A party structure notice lapses if the work hasn't started within 12 months of being served, so don't serve too early.

Can work start before the two months are up?

Only if the neighbour agrees in writing, or once an award has been made that allows it.

What if my neighbour ignores the notice?

After 14 days with no reply a dispute is assumed. You ask them to appoint a surveyor; if they still don't within 10 days, you can appoint one on their behalf under section 10(4).

Source: Party Wall etc. Act 1996 (applies in England and Wales).

Written by Guy Crouch BSc (Hons) MRICS, Director and Chartered Building Surveyor at Manchester Party Wall Surveyors. Last reviewed 3 November 2026. This page is general guidance, not legal advice. About our team